Projects
Tunnelled Sewer connection, Enfield
We were delighted to carry out this double sewer connection for an existing customer of ours, albeit this one was a bit of a challenge – in more ways than one…!
Objective
Our objective was to connect 6 new properties to the public sewer in the main road running thorough Enfield, in London. The connections were for both foul and surface water, one in the middle of the road and one on the far side of the road.
The challenges....
The sewers in the road that we had to connect to, were not particularly deep, the foul sewer being 3m deep and in the centre of the road, and the surface water being 2m deep, and on the far side of the road. The original Section 106 Approval that our customer had already arranged, had detailed new manholes to be built on both the surface water and foul sewers in the road. This would have meant a road closure lasting in excess of 2 weeks. Highways were unlikely to allow a road closure and diversion on a A-road, and for this length of time. We therefore approached Thames Water and requested the method of connection be changed to Junction Insertions, with the pipework being laid to two demarcation chambers built just inside the private shared driveway of the properties.
Thames Water agreed, and this would have shortened the work in the Highway to around 8 or 9 days, and might have allowed the works to be done under 2-way traffic lights instead. We had a meeting with Highways, but based on the width of the road, the location of both of the sewers to be connected onto, and also the depth of the excavations, it was still looking like it needed to be a road closure. But Highways weren’t keen on a road closure for this length of time, at such a busy location in London. Transport For London were also reluctant.
Highways suggested a shaft on one side of the road, and for it to be tunnelled to the other side of the road. However, existing services on the side of the road nearest the site, made a shaft in the road near-on impossible. Our only option left was to sink a shaft for tunnelling, in private property. But this meant denying the residents vehicular access for the duration of the works, which would take well in excess of one month. Our customer spoke to the neighbour, and a boundary fence was taken down between the new shared driveway and next door, enabling the residents of the new properties access via the neighbour’s driveway.
About the project
With the residents’ cars diverted and the front driveway gates locked shut, we lifted block paviours and put to one side. We excavated for the tunnelling shaft, 3m deep, and just over 2m wide in both directions. The excavation was quite wet at the bottom, around 2.5m down. We formed a concrete base at the bottom of the excavation and formed a sump, where we installed a pump that ran 24 hours per day and for the duration of the job.
We used trench sheets and heavy timbers to make the excavation safe. From here the tunnel was slowly excavated at a rate of just over 1m per day, with the top of the heading about 2m down from the road level. We found the foul pipe at the bottom of the tunnel, half way across the road, and the surface water at the top, and on the far side. The junctions were fitted and pipework laid back towards the site.
The tunnel was backfilled and packed with dry concrete as the pipes were laid back to the site. The tunnelling work took just under three weeks to complete. After that we excavated for and laid the small amount of pipework back into the two demarcation chambers. With the pipework all connected, the excavation was backfilled with gravel and type 1 compacted in layers, and the block paving reinstated.
Despite the initial challenges with method of connection, and then resistance from the authorities to close the road, we were able to complete these works and with pretty much no inconvenience to the general public, but just a little bit of hassle for the residents whilst the works were taking place. The nature of the works wouldn’t ordinarily have warranted a tunnelling solution, these weren’t particularly deep connections, but this was our only option if the road couldn’t be closed.
Timeline
Time to quote for the works: Less than a week
Time taken to obtain Section 106 Licence from AW: Our customer already had this, but we had to liaise with TW to get the method of connection changed, which added another two weeks to the process
Time taken to obtain Section 50 Licence from Highways: In excess of 2 months
Leadtime to use S50 Licence: 2 weeks – due in part to TTRO (Road Closure)
Time taken to do the work: 5 weeks
Total time: 17 weeks
Do you need a sewer connection needs doing? Click here to enquire.
Don’t leave it too late for a sewer connection, most people do! Read our article here: How long does it take to do a sewer connection?
Click here to see more of our case studies.






























































































































































































