If you need a new connection to the public sewer, it’s likely that the sewer is located beneath a public road, i.e. ‘The Highway’, either in the verge, a footpath or the road, and more often than not, in the road. Depending on the width of the road, the location of the sewer and the space needed to carry out the excavation safely, it may be necessary to temporarily close the road to traffic.

A temporary road closure can add several thousand pounds to the cost of a sewer connection. This is because there are normally two separate expenses: the highway authority’s charge for the legal road closure order and the cost of physically installing the closure and diversion.

For a breakdown of the wider costs, see how much a new sewer connection costs.

Why might a sewer connection require a road closure?

With it being most likely that the public sewer is in the road, connecting a new property to the sewer will often involve excavating within the public highway.

To undertake these works, the contractor will normally require a highway licence, commonly known as a Section 50 licence, from the relevant highway authority.

A Section 50 licence is required under the New Roads and Street Works Act 1991 for certain works involving the installation or retention of apparatus within the public highway.

Where there is sufficient space for traffic to pass the excavation safely – normally 3.5 metres or 3.0 metres, depending on the type of road – it may be possible to undertake the sewer connection using temporary traffic lights or other traffic management arrangements.

However, where the road is too narrow or the excavation is particularly wide, or there is insufficient space to maintain a safe traffic lane, the highway authority will often require a temporary road closure.

This usually involves obtaining a Temporary Traffic Regulation Order (TTRO).

 

What is a TTRO?

TTRO stands for Temporary Traffic Regulation Order, and is a legal order made by the highway authority that allows traffic to be temporarily prohibited or restricted from using a particular section of road. And it’s quite important to say that a TTRO does not always mean a closure, it can also mean just a restriction – but Highways’ fees are still the same, more on this at the bottom of the page…!

TTROs are commonly required for roadworks, including sewer connections undertaken under Section 50 licences.

They provide the legal framework for the temporary traffic restrictions needed to carry out the works.

However, obtaining a TTRO is not simply a matter of paying a fee and receiving permission to put up a Road Closed sign.

There is an administrative and legal process that must be followed, and this is why the fees can be substantial.

What does the TTRO fee pay for?

When a highway authority charges for a Temporary Traffic Regulation Order, the fee contributes towards the administrative and legal work involved in arranging the temporary restriction.

Depending on the authority and the circumstances, this can include:

  • Processing and assessing the application.
  • Preparing the legal order and associated documentation.
  • Advertising the proposed restrictions through the required public notices.
  • Consulting with or notifying the police and emergency services.
  • Notifying bus operators and coordinating any affected bus routes.
  • Checking the proposed diversion route and its suitability.
  • Coordinating the closure with other planned roadworks.
  • Informing other relevant organisations about the restrictions.

The process is intended to ensure that a road is not closed without proper consideration of the consequences for other road users, local residents, businesses and public services. On our Bourne End sewer connection project, despite the road being closed, we still carried out the work in sections so residents could still reach their properties during the closure

For example, a road closure may affect a scheduled bus route, access for emergency vehicles or the availability of an alternative route for heavy goods vehicles.

The highway authority needs to consider these issues before permitting the works to proceed.

Importantly, the TTRO fee generally pays for the legal and administrative arrangements. It does not pay for the physical road closure itself.

Interesting fact: Part of Highways’ job during the TTRO application process is to notify the emergency services of TTRO road closures, allowing them to plan alternative routes and update their sat nav systems to avoid closed roads.

Traffic Management Plans – More Than Just a Drawing

As part of our service of taking care of a TTRO application, we have to get a third-party company to design a Traffic Management Plan showing the proposed road closure and the diversion route, which has to detail where every single sign is going to be placed on the Highway. And it’s not unusual for a road closure and its diversion route to require upwards of 40 different signs.  On a recent road closure that we took care of, which started at 08:30 on a Monday, the traffic management company had to start putting signs out at 03:30.

These are submitted to the Highway Authority for approval, with stakeholders such as emergency services and bus operators potentially providing feedback.

Highways may request changes, meaning plans can go back and forth several times before final approval. This process can take considerable time and is another reason why road closures must be planned well in advance

How much does a TTRO cost?

TTRO fees vary considerably between different highway authorities.

The following are examples of published charges for planned roadworks-related TTROs in counties across southern England and around London.

Highway authority

Example TTRO charge

Kent County Council

£1,310

Hertfordshire County Council

£2,068

Buckinghamshire Council

£2,410.45

Oxfordshire County Council

£2,850–£3,000

West Berkshire Council

£3,334

Essex County Council

£1,426.72

In Oxfordshire, for example, the charge differs depending on whether the affected road carries a bus route.

These examples demonstrate that the TTRO charge alone can amount to thousands of pounds, before a contractor has even excavated the road.

The precise fee will depend on the highway authority, the type of order required and the charging schedule in force at the time of application. Additional charges may also apply in certain circumstances.

The additional cost of physically closing the road

This is the second expense, and one that customers do not always appreciate.

Paying the council for the TTRO does not mean the council will arrive and close the road for us. They only take care of the application and all the legals, it’s down to us to physically close the road.

As the contractor we must arrange and pay for the physical traffic management required to implement the closure.

This can include:

  • Preparing a suitable traffic management plan.
  • Supplying and installing Road Closed and diversion signs.
  • Providing barriers, cones and other necessary equipment.
  • Signing the diversion route at appropriate junctions.
  • Transporting the equipment to and from the site.
  • Inspecting, maintaining and adjusting the traffic management while the works are underway.
  • Removing the equipment and reopening the road once the works are complete.

On a relatively straightforward sewer connection, the physical closure and diversion arrangements can often cost up to £1,000, and often considerably more.

The actual cost depends on the length and complexity of the diversion, the number of signs required, the duration of the works and any additional traffic management measures imposed by the highway authority.

For example, closing a quiet residential road with a short alternative route will generally be less involved than closing a busy through-road requiring a lengthy diversion through several surrounding villages.

More complex closures may require additional operatives, temporary signals, specialist equipment or arrangements to maintain access.

These costs are separate from the TTRO fee and from the actual sewer connection works.

What might the total road closure cost be?

Consider a sewer connection requiring a planned TTRO with a highway authority fee of £2,000.

The costs might be:

Item

Example cost

Highway authority TTRO fee

£2,000

Physical road closure, signage and diversion

£1,000

Total additional road closure costs

£3,000   

This is an illustrative example, not a quotation. It excludes the Section 50 licence, the excavation, the actual sewer connection, reinstatement and any other applicable charges.

It also assumes a relatively straightforward road closure.

The important point is that road closure expenses can add a significant amount to the overall cost of a new sewer connection.

How long does it take to arrange a road closure?

TTRO applications generally require considerably more advance notice than many customers expect.

Depending on the highway authority, applications for planned road closures may need to be submitted approximately eight to twelve weeks or more before the proposed works.

This allows time for the necessary checks, coordination, consultation and legal advertising.

Consequently, even where the sewer connection itself can be completed in only a few days, arranging the road closure can introduce a much longer lead time.

At JW Clark, we recommend identifying any likely road closure requirements as early as possible, particularly where the connection is needed for a new-build property or development with an intended completion date.

Beware the TTRO that isn’t actually a road closure…..

There is one final point worth understanding, and it is something we have encountered on many sewer connection projects over the years.

Just because you have paid for a TTRO does not necessarily mean you can completely close the road and prevent all vehicles from passing through.

For example, the highway authority may determine that a minimum safe traffic width, perhaps around 3 metres depending on the circumstances, cannot be maintained alongside the excavation.

A TTRO may therefore be necessary to impose temporary restrictions.

You might reasonably assume that this means the road can simply be closed for the duration of the works.

Unfortunately, it isn’t always quite that straightforward.

The highway authority may still insist that access is maintained for some residents or certain other vehicles, or that the road is only closed intermittently.

We have encountered circumstances where measures such as the following have been required:

Using steel road plates to maintain access

Where residents need access to their homes, it may be necessary to temporarily cover an excavation with a suitably designed and secured steel road plate, allowing vehicles to pass when it is safe to do so.

This can create additional work and expense, particularly where excavations must be made safe and temporarily covered at certain times.

Closing the road for only short periods

In other circumstances, the highway authority may permit the road to be closed to traffic for only short periods, perhaps 15 minutes at a time, before access must be restored.

This can be particularly challenging during sewer connection works, where excavations, pipe installations and reinstatement operations are not always easily interrupted.

These arrangements must be assessed and agreed in advance, and any temporary access across an excavation must be properly engineered and safe.

A remark from a highways officer that has stayed with us

During discussions about one particular scheme, a highways officer once explained the situation to us rather memorably:

“A TTRO is not necessarily a Road Closure, it’s what we want it to be.”

It was a rather blunt way of putting it, but the point was clear.

A TTRO is a legal mechanism allowing the highway authority to impose temporary restrictions. The precise arrangements are determined by the authority and the conditions applicable to the works.

In other words, a TTRO gives the legal authority for the agreed traffic restrictions; it does not automatically give a contractor unrestricted control over the road.

It is therefore important to establish exactly what restrictions will be permitted before committing to the works.

At JW Clark, our experience of dealing with highway authorities helps us identify these potential complications, allowing us to plan the sewer connection and associated traffic management arrangements as effectively as possible.

Need a sewer connection that involves roadworks?

JW Clark Ltd specialises in public sewer connections, including installations requiring Section 50 licences, Temporary Traffic Regulation Orders and associated traffic management.

We undertake sewer connection works across areas served by Anglian Water, Severn Trent Water and Thames Water.

We can assist with the applications, highway arrangements, traffic management and physical installation, helping customers understand the likely costs and requirements before works commence.

If you are planning a connection to the public sewer, contact JW Clark Ltd for advice or a quotation.

Find out more about our sewer connection services

Do you have a project you wish to discuss?

Latest Posts

How Long Does a Septic Tank Soakaway Last?

If your property has a septic tank, you may assume that regular emptying will keep the system working

Who Can Legally Carry Out a Sewer Connection in a Public Road?

Who Can Legally Carry Out a Sewer Connection in a Public Road? If you’re building a new property

Will the Water Authority Adopt My Pipework on a New Sewer Connection?

One of the most common questions we are asked when carrying out a new sewer connection is: “Will