Pump Chamber installation & sewer connection, Cirencester

Pump Chamber installation & sewer connection, Cirencester

We were pleased to carry out this sewer connection for three neighbouring properties in Cirencester, Gloucestershire, replacing an existing sewage treatment plant that had been causing the residents considerable problems.

Location
Cirencester, Gloucestershire
Client
Three private households
Value
£30,000
Sewer Connections - Building-Site-Scene - JW Clark

Objective

Our objective was to connect three existing residential properties to the public foul sewer, replacing a shared sewage treatment plant which was not working as it should. It had been installed only a few years ago, and although the plant appeared to have been sized correctly for the number of properties, the soakaway or drainage field was not suitable for the volume of effluent from these three properties combined. As a result, the plant was regularly filling up and required frequent tanker emptying, causing considerable inconvenience and expense for the residents. Click here to read our article How long does a soakaway last.

In addition, new rules since 2020 prohibit installation of a septic tank or treatment plant where a public sewer exists within 30 metres of the property boundary, so a treatment plant should never have been installed in the first place. 

In any case, the public sewer was only a few metres from the properties, so connecting to the mains was a much more sensible long-term solution.

The challenges....

Although the public sewer was relatively close, the properties were at a level which meant that a gravity connection wasn’t possible. We therefore needed to install a new sewage pumping station, which would collect the foul water from all three properties and pump it to the public sewer in the road.

As usual with sewer connections, there were also various applications and permits to organise, including the Section 106 application to Thames Water and the necessary arrangements with Highways, namely the Section 50 application.

Another important consideration was that all three properties were occupied, and the residents obviously needed to continue using their toilets, bathrooms and kitchens throughout the works.

About the project

With the permits arranged with the water authority and Highways, we brought plant to site and dug trial holes in the front driveway to identify a suitable position for the underground pump chamber among the existing services. The new sewage pumping station was installed within the private property, set in concrete and connected to the existing drainage serving the three houses. We use Marsh Industries pump chambers throughout our installations, and we are Marsh Industries Approved Contractors.

With the pump chamber installed, we then laid a new 63mm MDPE ‘rising main’ from the pumping station towards the highway. At the boundary we built a ‘break chamber’ – this is the point where the pipework changes from being a ‘rising main’, with 63mm MDPE pipe, to gravity pipework, for which we used 100mm clay pipes. As the break chamber was to be in the entranceway to the shared driveway, we finished it with a D400 manhole cover.


With the Section 50 in place and our roadspace booked, we excavated in the Highway for the clay pipework. The manhole in the Highway that would be our connection point, was unusually shallow, at only about 500mm deep. We core-drilled into the manhole, our connection method being ‘direct connection into a manhole’ Click here to read more about connection methods. Once the connection had been inspected, we backfilled the excavations and reinstated the tarmac in the carriageway.
One of the most important parts of the job was ensuring that the residents could continue using their drainage throughout the works. We arranged the installation and final changeover so that the three households were not left without a functioning sewage system.
With the ‘switchover’ done, and the new pump chamber commissioned and tested, the old treatment plant was then decommissioned, with the three properties connected to the public sewer via their new pumping station.
This was a particularly satisfying project for us, as the residents had been dealing with a troublesome private sewage system for some time. 

The three households now discharge to the public sewer through their new shared pumping station, removing their reliance on the troublesome treatment plant and failed soakaway. The residents no longer depend on the garden’s ability to absorb treated wastewater.

The new pumping station will require some ongoing care. Our factsheet, Aftercare for Pump Chambers, explains the servicing and maintenance responsibilities that come with these systems.

Timeline

Time to quote for the works: Less than a week

Time taken to obtain Section 106 Approval from Thames Water: 3 weeks 

Time taken to obtain Section 50 Licence from Highways: 6 weeks

Leadtime to use S50 Licence: 4 weeks

Time taken to do the work: 2 weeks

Total time:  15 weeks

If your treatment plant or soakaway is causing problems, or your property cannot connect to the public sewer by gravity, contact JW Clark to discuss your project.

Don’t leave it too late for a sewer connection, most people do! Read our article here: How long does it take to do a sewer connection?

Click here to see more of our case studies.

Sewer connection & pump station installation, Dagnall

Projects

Sewer connection & pump station installation, Dagnall, Buckinghamshire

We were delighted to undertake these works for 7 private properties in Dagnall, Buckinghamshire

 

Location
Dagnall, Buckinghamshire
Client
Private client
Value
£55k
commercial contracts

Objective

Our objective was to get 7 properties off a Treatment Plant which wasn’t fit for purpose, and connect them to the public sewer.

About the project

We were first approached by our customer in September 2024. They had a treatment plant which was shared by 7 people. The treatment plant appeared to be reasonably up to date and fit for purpose, apart from the fact that the effluent wasn’t dispersing properly into the ground.

As with any treatment plant, they are only as good as the quality and volume of the land drainage that is put in to disperse of the effluent thereafter, and in this case there wasn’t enough room within the boundaries of the site, for the volume of land drainage required for this size of treatment plant, and a lesser amount had been installed years ago, as a result.

We spent a couple of months paying multiple visits to site and playing about with the levels on site, to try to get a gravity sewer connection to work. The sewer was about 90 metres from the nearest sewer, and we eventually had to concede that we couldn’t get the fall. Therefore we would have to price for a sewerage pump chamber, to pump the waste nearly the full 90 metres.

As the pump station was to be shared across several properties, the residents were wary of the pump station and the ‘rising main’ to the sewer, remaining private and under their ownership. They preferred that everything be adopted by Thames Water.

However, after a long process lasting in excess of 1 year, the Section 104 process became too expensive. We had a detailed consultation period with the residents, whereby we assured them that the risks associated with a traditional ‘Section 106’ application (whereby they retain ownership of the pipework, including in the Highway) were not so excessive. And they decided to go down the Section 106 route. Nothing would be adopted by Thames Water, apart from the final connection into their public sewer. Click here to read more about adoption of pipework. 

S106 & S50 applications process

As with any sewer connection, a Section 106 is always required from the Water Authority, basically to get permission to connect to the public sewer. In this instance, Thames Water were the sewerage provider for the area, so we made our application to them on behalf of our customer. Click here to read more about the Section 106 process.

Having received the S106 approval from TW, we were able to apply for the Section 50 to Highways, which is basically the application to ‘dig up the road’. You cannot apply for a S50 until you have the S106 in hand, as Highways are duty bound to ensure you have a S106 as part of their S50 process. A Section 50 application can be an extremely lengthy process and can take several months or more, to process. Click here to read more about the Section 50 application process.

With all applications approved we started in private property, installing the pump chamber. There had been concerns about the water table – the pump chamber was about 3m deep and we were worried we would encounter water at 1-2m deep. However the work was done in August and there had been little rain over the previous couple of months, and we didn’t encounter any groundwater. The pump chamber was concreted in, as per manufacturer’s guidelines.

We then proceeded to undertake the works in the Highway. The connection point was at a busy roundabout, but only about 1.5m into the carriageway. We were able to maintain 3.5m for traffic, after we had set up our work zone, so we were able to undertake the works using simple ‘Give & Take’ Traffic Management, with there being no need for traffic lights. The method of connection was ‘Direct connection into a manhole’. Click here to read about different methods of connection.

With the connection made into the public sewer, we then continued to lay 100mm clay pipe towards the location of our ‘break chamber’. This is the point at which the pipework changes from gravity pipework to pumped pipework. The gravity pipework is 100mm clay pipe, and after the break chamber it changes to 63mm MDPE pipework. It is not possible to pump all the way into a public sewer, the final piece of pipework always has to be by gravity.

From the break chamber and towards the house we continued to lay the 63mm MDPE pipework, which was laid at 600mm cover. The MDPE pipework is lay in a sand surround, so it can ‘flex’ ever so slightly. And prior to backfilling, we put a layer of warning tape in to help protect the pipework in the future. The majority of the MDPE pipework was laid in the grass verge, with the final few metres in tarmac footway, before continuing into private property.

In private property, the last bit of pipework was laid in the gravel driveway and connected into the new pump camber that had been installed at the start of the job.

A ‘kiosk’ was installed adjacent to the pump chamber. This houses the control panel for the pump chamber, which co-ordinates the floats and controls when the pump is activated within the chamber. From the kiosk we laid a duct to an electric source on one of the seven houses. An electrician made the connection into the kiosk, and a third party ‘commissioner’ did the work to commission and test the new pump chamber.

With the pump chamber connected, tested and commissioned, we did the switchover from the old system to the new. We did this in such a way that the residents were not without their foul system for any amount of time, they were able to continue using their toilets etc, as usual. It was great to get this job completed for these customers after the long and arduous applications process, that took just over two years.  

Timeline

Time taken to quote for the works: 2 months

(Section 104 process pursued for 18 months and eventually abandoned)

Time taken to obtain Section 106 Licence: 4 weeks

Time taken to obtain Section 50 Licence: 3 weeks

Leadtime to use Licence: 6 weeks

Time taken to do the work: 4 weeks

Total time: 25 months