We were pleased to carry out this new sewer connection for two neighbouring properties in the village of Thorpe Malsor, near Kettering, Northamptonshire.

The two properties had previously been connected to a shared private drainage system which discharged into a neighbouring property’s septic tank. The shared septic tank was very old and non-compliant. The owners wanted to separate their drainage from this arrangement and connect directly to the public foul sewer. Click here to read our factsheet Are septic tanks illegal?

Location
Thorpe Malsor, Northants
Client
Two private households
Value
£25k
Sewer Connections - Building-Site-Scene - JW Clark

Objective

Our objective was to disconnect the existing private drainage serving the two properties and install a new gravity sewer connection to the public foul sewer.

The properties shared an existing drainage pipe running along a private lane, and the proposed connection involved laying approximately 75 metres of new underground drainage within private property, together with the connection works in the public highway.

The challenges....

Our initial investigation involved locating existing manholes, carrying out level surveys and considering several possible routes for the new drainage.

One option involved installing a sewage pumping station, but we were also able to identify an alternative route which would allow the properties to connect by gravity, avoiding the additional expense and ongoing maintenance associated with a pump.

However, the proposed route passed through privately owned land, and before work could proceed, various legal agreements, access permissions and arrangements with neighbouring landowners needed to be finalised.

These matters proved considerably more complicated than anticipated, and the private property element of the project was delayed on numerous occasions for this reason.

We therefore agreed to split the work into two stages, completing the public highway connection first, while allowing time for the outstanding legal matters to be resolved.

About the project

We initially visited the site to carry out investigations into the existing drainage and taking levels to establish the most practical connection route.

Following discussions with the owners, we agreed on the gravity connection option.

The first stage involved obtaining the Section 106 from Anglian Water and the Section 50 from Highways, before excavating within the public road to make the connection to the existing public foul sewer.

Highways agreed to allow us to carry out these works using ‘give and take’ traffic management, rather than traffic lights or a full road closure, which helped keep disruption and costs to a minimum.

The pipework installed within the public highway was 100mm vitrified clay, as required for the connection. Connection method was into an existing manhole. See here for different connection methods for sewer connections.

These works were successfully completed within 4 days.

The remaining works within private property were considerably delayed while the owners and neighbouring landowners worked through the necessary legal agreements.

Throughout this period, we remained in regular contact with everyone involved, rearranging our programme as required and helping to resolve practical questions concerning the drainage specifications and access arrangements.

 

Eventually, with the necessary permissions in place, we returned to site to complete the private drainage works.

These involved excavating through the existing tarmac lane and installing approximately 75 metres of new 110mm plastic underground drainage, together with new inspection chambers and the connection to the previously completed highway works.

Once the new drainage was connected, we backfilled the excavations and reinstated the private driveway.

Both properties were successfully connected to the public foul sewer, and the original pipework leading to the neighbouring septic tank was disconnected and permanently taken out of use.

Although this project took considerably longer than anyone had originally anticipated, we were pleased to have brought it to a successful conclusion.

It was especially satisfying to provide the two households with their own connection to the public sewer, removing their dependence on the neighbouring septic tank.

Following completion, our customer shared the Google review shown here, describing their experience of working with JW Clark

Timeline

Time to quote for the works: Less than a week

Time taken to obtain Section 106 Approval from Anglian Water: 3 weeks 

Time taken to obtain Section 50 Licence from Highways: 6 weeks

Leadtime to use S50 Licence: 3 weeks

Time taken to carry out works in the Highway: 4 days

Delay in waiting for legals to be arranged for work in private property: More than one year while legal agreements and access permissions were finalised.

Time taken to do the work in private property: 2 weeks

Total time:  15 weeks – but with the 1-year delay in between

If your treatment plant or soakaway is causing problems, or your property cannot connect to the public sewer by gravity, contact JW Clark to discuss your project. Click here to read our factsheet Is a septic tank illegal?

Don’t leave it too late for a sewer connection, most people do! Read our article here: How long does it take to do a sewer connection?

Click here to see more of our case studies.

Related Works