Sewer connection and associated utilities works, Creaton

Projects

Sewer connection and associated utilities works, Creaton, case study

We were approached by David, a friend of his recommended he contact us regarding his project whereby he required a sewer connection and various other utilities laying from his barn conversion, all the way down to the Highway, 250 metres away.

Location
Creaton, Northants
Client
Private customer
Value
circa £40k
Transport-Truck-02

Objective

Our objective was to connect to the sewer in the Highway and lay pipework to the boundary with the property. And then to lay drainage including pipework & manholes, from the boundary with the Highway, all the way to the location of the barn conversion, over 200 metres away. We also laid other services in the same trench.

About the project

.

As is usual, we took care of both the Section 106 to Anglian Water, and also the Section 50 to Highways. Our customer already had drawings for the proposed drainage in the site, but we asked for amendments to be made to include the work in the Highway. These included for the pipework to be laid across the road to the connection point in the footpath. A ‘drainage drawing’ submitted to the Water Authority for a Section 106 has to include the pipework, detailing the pipe material & size, it has to detail the size of the existing sewer we are to connect onto, and the method of connection. In this case the method of connection was ‘Junction Insertion’.

With the drainage drawing amended, we facilitated the Section 106 application to Anglian Water. This was passed within a couple of weeks, and with the Section 106 Approval Letter in hand we made the application to Highways for the Section 50 – you cannot legally apply for a Section 50 to ‘dig up the road’ before you have the Section 106 from the water authority. Highways have a duty of care to ensure we have permission to connect onto the target apparatus, in this case the public sewer. As part of our Section 50 application to Highways, we nominated ‘give and take’ traffic management, as the road was a quiet ‘dead-end’ road without much traffic. The Section 50 was approved within 3 weeks, as is usual for a simple S50 application – but beware, the application can often take much, much longer. Click here to find out more.

We had to give 3 weeks’ notice to Highways that we wished to use our Section 50 Licence. We started on the ‘other’ side of the road to the site, in the footpath, where we believed the public sewer to be. We found the pipe at 1.6m deep, and under various other services. We made the connection onto the public sewer on day 1, and this was inspected and passed by Anglian Water on day 2. With the connection made and approved, we worked our way across the road, laying 100mm clay pipes in the direction of the site. We completed the work in the road in two halves, reinstating the first half with tarmac before continuing with the second half. The work in the Highway was complete in 6 days, including all reinstatement.

We arranged with our customer to carry out the works in private property straight after the work in the Highway. The work in private property included laying 110mm plastic pipework for the foul drainage, and various manholes along the way, and also other services relating to the barn conversion. These included 125mm electric duct, 90mm BT duct, 32mm water pipe and also a spare 63mm electric duct for future use, i.e. electric gates or similar.  

We dug various trial holes and CAT-scanned the site for electric, and luckily found there to be no services in the first half of the route. There was some electric in the second half nearest the barn conversion, we marked these and also dug exploratory holes to ascertain depth of cables etc.

The electric ducts were supplied by National Grid, as is usual, and we collected them from their local depot. We dug our trench about 1.2m deep. The foul and the water pipe were laid towards the bottom, the foul in gravel surround and the water in sand surround, with warning tape to cover. The two electric ducts were laid above and also the BT, and laid in sand surround and with more warning tape to finish.

The services were all laid to one side of the farm track leading to the barn conversion, but we had two tarmac roads to cross further up, which we reinstated with tarmac afterwards. We pulled draw cords through the ducts to enable cables to be pulled through later. With the total distance of pipework being in excess of 200 metres, and with four separate rolls of 32mm water pipe being laid and joined together, we decided to fusion-weld the water pipes together so we could be sure that the joints were 100% watertight under pressure later on when the connection was done in the Highway by Anglian Water. The most common way to join water pipes together is by way of ‘compression joints’, but it is harder to know for sure that the connections are good, in advance of the pipes being live, and we wanted to have confidence that we could backfill in advance of this. 

All trenches were compacted in layers and reinstated, whether it be with grass or topsoil, or tarmac where we crossed roads further up. The ground at the top was particularly wet, and some of the foul pipe runs were in excess of 1.8m deep here. We found various land drains running through our trenches at this point as well, which made our job harder, with water pouring into our trenches as we were excavating and laying various pipes and ducts. With all of the trenchwork complete, we went back to the bottom of the track and tidied the site from start to finish, scraping the farm track as we went, and hosing and sweeping where required

Timeline

Time taken to quote for the works: Less than 1 week

Time taken to obtain Section 106 Licence from AW: 2 weeks

Time taken to obtain Section 50 Licence from Highways: 3 weeks

Leadtime to use S50 Licence: 3 weeks

Time taken to do the work: 3 weeks

 

Total time:  12 weeks

Do you need a sewer connection needs doing? Click here to enquire.

Don’t leave it too late for a sewer connection, most people do! Read our article here: How long does it take to do a sewer connection?

Click here to see more of our case studies.

Vehicle crossover, Knuston

Projects

Vehicle crossover and tarmac drive, Knuston

We were approached by a regular customer of ours, who had been redeveloping a large property in the village of Knuston in Northamptonshire. The driveway had already been block-paved in the main. The entranceway was being made bigger with new walls and electric gates, and the customer wanted tarmac for this part. There was an existing crossover, in tarmac, but it was very tired and falling to bits, so it was decided to resurface this at the same time.

Location
Knuston, Northants
Client
Private customer
Value
£x,xxx
Sewer Connections - Building-Site-Scene - JW Clark

Objective

Our objective was to lay tarmac in within the new entranceway and between the new stone walls, but also to excavate the existing crossover and to relay with tarmac, all at the same time.  

About the project

Whilst our customer was having completing the remainder of the block paving within the site, and building the walls either side of the new crossover, we approached Highways regards resurfacing the existing crossover. We were told this would need a Section 171, as opposed to a Section 184, which is to create a new crossover from scratch. In deciding method of traffic management we had to consider that the footpath would be out of action for 2 days. As there was no footpath on the other side of the road, we didn’t have the option to simply close the footpath and send the pedestrians over to a footpath on the other side of the road. The pedestrians would have to go in the road, via a dedicated ‘pedestrian walkway’, and for this to be possible we would need 2-way traffic lights to close the lane nearest. This would also enable us to park works vehicles adjacent to the site.  

We set up the traffic lights at 8am on day 1. We proceeded to excavate the existing crossover to the required depth for type 1 MOT and for the crossover construction which in Northamptonshire is 100mm of 20mm-size base course, and 20mm of 6mm ‘top-coat’. The area to be laid in tarmac extended beyond the crossover at the front, between the new walls that had been build to the front of the property, and all the way to where the block paving had been laid in the site. The type 1 that had been laid and compacted by the customer was checked for levels and didn’t require any further work.

The spoil was removed from site by the end of day 1 and preparations made to tarmac the following day. On day 2 we arranged for base course to be delivered at 8am, and it arrived shortly after. The tarmac was delivered on a lorry with chutes to the rear, which we used to fill wheelbarrows. The base course was in and laid before 11am. The 6mm ‘top-coat’ was delivered around 1pm and this was in and compacted within an hour and a half.

The new crossover and tarmac laid to the rear of the crossover was cool to walk on within a couple of hours. The traffic lights were taken down ready for the heavier teatime traffic, but we kept traffic off the crossover until the following morning, when it was open and for the customer to use.

Timeline

Time taken to quote for the works: Less than 1 week

Time taken to obtain Section 171 Licence: 1 week

Leadtime to use S171 Licence: 4 weeks

Time taken to do the work: 2 days

Total time: Just over 6 weeks

Do you need a vehicle crossover doing? Click here to get a quote. Click here to see more Vehicle Crossover case studies. 

Treatment Plant Installation, Preston Deanery

Projects

Treatment Plant, Finedon, Case Study

Location
Finedon, Northants
Client
Private customer
Value
Circa £12k

 

We were approached by a domestic customer in Preston Deanery, Northants, They had an old septic tank, and this was preventing them from selling their house, as septic tanks are no longer compliant in most cases.

Sewer Connections - Building-Site-Scene - JW Clark

Objective

Our objective was to install a new septic tank, including electrical connection. Then to lay pipework to a live watercourse, and to switch the old foul system over to the new Treatment Plant.

We did a site survey first, to ascertain levels, including levels of the existing foul system and septic tank, and how it would work with the inlet level on a new Treatment Plant. We also had to factor in the level of the watercourse (the stream) relative to the outlet on a new Treatment Plant. The house had 6 bedrooms, so would ordinarily need an ‘8-person’ Treatment Plant. However, the property had he potential to add more rooms and bedrooms, and was soon to be sold, so we opted for a 10-person plant to allow for extra future capacity. The levels didn’t work very well with the stream – the outlet level on the plant was about the same height as the level of the stream in summertime. With the level of the stream likely to be much higher during wetter months, this would put the outlet of the plant below the level of the stream, which would have the effect of flooding the plant. A one-way non-return valve would be solution to prevent the plant from being flooded, but still, the effluent from the plant would not be able to discharge for many months of the year.

We therefore opted for a ‘pumped outlet’ whereby the effluent is pumped uphill and then discharges into the stream at the very top, and away from the level of the stream down below.

We started the work in September, but the weather wasn’t great, so we brought track mats to site, to move the plant about the garden without causing too much damage to the grass. We excavated for the Treatment Plant first, and installed it on a concrete slab, with full concrete surround. The plant was installed in order that the inlet was low enough for the existing foul drainage system to be able to discharge into it. This put the plant about 250mm below the existing grass, so we needed a riser fitting to the plant, which was supplied to us by the manufacturer, Marsh Industries. We’ve been working with Marsh for nearly 20 years and always install their Treatment Plants, which are made to order.

With the plant installed, we excavated for and lay the outlet pipe, this was a black 32mm MDPE pipe. This was laid to within 3m of the stream, and then put into a 110mm underground drainage pipe. The pipe was surrounded with ‘fill’ sand, and warning tape laid above, and then the trench backfilled and the grass reinstated.

We then excavated for the electric feed to the plant, this was laid in a black 63mm duct. The electric feed was taken from one of the outhouses, with an isolator fitted, as per Building Regs. We instructed an electrician, who connected up by the ‘blower’ which blows oxygen into the plant, and also the pump which pumps the effluent out to the stream, when the effluent in the plant gets to a certain level.

We then excavated for and made the switchover from the old system to the new system, which included fitting a new manhole where the old pipework met our new pipework. All systems were tested, and the remainder of the garden and gravel driveway reinstated.

The work took a bit more than a week, and as with an install of any Treatment Plant, it’s good to see a satisfied customer, and no longer with the worry of a non-compliant septic tank. 

 

Our customer was kind enough to leave us a 5-star review on Google afterwards.  Click here to see our Google reviews

Timeline

Time taken to quote for the works: Less than 1 week

Our leadtime to carry out the works: 6 weeks

Time taken for Treatment Plant to be manufactured: 6 days

Time taken to do the work: 6 days

Unfortunately it took over two weeks for the customer to obtain the full Building Control approval certificate. Whilst this is usual, it did hold up the sale of the property.

If you need a Treatment Plant installling and the project is part of selling a property, be sure  to contact us with as much notice as possible. 

Gabion retaining wall, Irthlingborough

Projects

Gabion stone Retaining wall, Irthlingborough, Case Study

Longstanding customer of ours, Whitworths, asked us to construct a gabion stone retaining wall to enable extension of existing parking area at their site in Irthlingborough.

Location
Irthlingborough, Northants
Client
Whitworths
Value
£xx,xxx
Sewer Connections - Building-Site-Scene - JW Clark

Objective

We were tasked with creating a gabion stone retaining wall 1.8m high and 200m long, to enable our customer to extend their existing hardstanding area, in preparation for future expansion. 

About the project

A gabion stone wall had been started many years ago adjacent to the boundary with surrounding fields. This had been done with granite stone. Our customer asked us to extend this to bring it up to a height in order that the existing hardstanding area could be extended closer to the site boundary.

The design included a foundation for the baskets, made with 6F2 recycled concrete. This was already on site and had been processed on site recently, as part of a demolition project. We compacted the 6F2 in layers to bring it up to the required level. The gabion stone baskets were installed with a slight fall to the site, to help with the pressure of the ground that would be put up against the wall later. We used good quality gabion baskets for this, there are varying qualities of gabion baskets on the market, but from previous experience some of the cheaper options available tend to ‘bulge’ in time with the weight. We’ve also learnt to install the internal straps that are available and that go inside the baskets prior to filling them with stone, this also helps to reduce bulging.

The original gabion stone wall that had been done many years ago had been done with granite stone, however we used ironstone on this occasion, this with cost in mind and also local availability. With the baskets in place, we started to fill them with stone. The stone can, generally, be put into the baskets with a machine. But there is some sorting required, which had to be done by hand, particularly with the face of the wall and on top, where the stone will be seen. 

The wall was 1.8m high in places and stepped back from the watercourse at 45 degrees. With all of the gabion wall constructed, we put some of the excess 6F2 that was on site, up against the wall. The work to bring the site up to the required level is a long term project, but is ready to be completed at a later date.

It was a pleasure to carry out this work for a longstanding customer of ours, and on our doorstep too, in Irthlingborough. A lot of our employees actually live in the town. We look forward to continuing our working relationship with Whitworths in the future.

Do you have a similar project you would like a price for?  Please visit our website and fill out our contact form. We undertake all types of groundwork projects, both commercial and domestic, see here for our full list of services www.jwc.co.uk 

Treatment Plant Installation, Silsoe, Bedfordshire

Projects

Treatment plant installation, Silsoe, Case Study

We were approached by our domestic customer in Silsoe, Bedfordshire, who had an old septic tank with various problems and which was not compliant. They wanted a new Treatment Plant fitting in its place.

Location
Silsoe, Bedfordshire
Client
Private customer
Value
£13k
commercial contracts

Objective

Our objective was to install a new treatment plant and re-route the existing drainage to this, from the old septic tank. The septic tank was not particularly old, but was not compliant to discharge effluent into the ground under new EA and Building Regs guidance, and the land drainage or soakaway was not coping well in discharging the effluent, this is one of the most common reasons for septic tanks failing. 

About the project

Prior to ordering the new treatment plant, we had to take some levels to site to ascertain the invert level of the existing drainage, this level is critical in determining the length of the ‘neck’ on the new plant, which are all made to order. We use Marsh Industries for all our Treatment Plants and Pump Stations, and have been doing so for over 15 years now. We gave our customer the choice of either an 8-person plant or a 10-person, and they chose to go with the 8-person.

We started by excavating for and installing the new treatment plant, leaving all of the existing drainage running into the old septic tank whilst the bulk of the work was being carried out on site. The plant was laid on concrete and completely surrounded in concrete. The plant has to be filled with water whilst the concrete is being packed around the outside, with the level of the concrete never coming higher than the level of the water inside. On the following day, with the concrete having ‘cured’, the water can then be pumped out. The strength of the plant is dependent on the concrete surround, they are not designed to take the weight and the pressure of the ground around the outside without the concrete.

The effluent from the new Treatment Plant was to disperse into a watercourse on the boundary of the property, which is by far the best way to legally discharge of the effluent, and it’s also the cheapest way, much cheaper than excavating for and laying land drainage. The levels worked for the effluent to discharge to the stream by gravity, which was great. This pipework was installed after the plant install, and the grass reinstated on top.

The plant was conveniently located adjacent to a double garage, with full electrics. This was ideal for connecting the plant up to. We excavated for and laid a 63mm black electric duct to the outside of the garage. The duct was surrounded in sand with electric warning tape to cover, the trench backfilled and the grass reinstated. Our customer appointed their own electrician, but we liaised with him as to what was required. As per building regs, a treatment plant needs its own isolator, which the electrician sited on the inside of the garage. Quite often they are sited outside, but either is acceptable.

We then had to divert the existing drainage from the old septic tank, to the new treatment plant. We excavated for all the pipework first before making the switchover. With everything dug out ready for the final piece of pipework, we ‘bunged’ the pipework from the house and switched the pipework over. This way, our customer was able to continue to flush their toilets and carry on using the system throughout.

The existing septic tank was quite extensive and the customer asked that we fill this huge void underneath their driveway, with some of the spoil that had been generated from the excavation for the new treatment plant. To enable us to do this, we asked the customer to have the septic tank emptied one last time after the switchover had been done. This enabled us to fill it with the excavated material. We compacted it best we could on top, and reinstated with grass, getting rid of all the old manhole covers on the top of the septic tank.

With the electrical connection done by the customer’s electrician we checked the new system over and everything was working great. We reinstated some tarmac on the edge of the driveway, but most of the reinstatement was in grass. We managed to salvage most of the turf that we had taken up and put this back, which just left a few gaps here and there, which we filled with fine-grade topsoil and grass seed.  

More info

Do you need a treatment plant installing? Click here to contact us for a quote

If you want to know more about treatment plants, click here to read our dedicated FAQs page

We have in excess of one hundred 5-star Google reviews, click here to read our reviews!

New Vehicle Crossover, Kettering

Projects

New Vehicle Crossover, Kettering

Location
Kettering, Northants
Client
Astar Living
Value
Circa £7k
Sewer Connections - Building-Site-Scene - JW Clark

Objective

We were approached by a regular customer of ours, Astar Living, to install a new vehicle crossover on Windmill Avenue in Kettering. The customer had already approached North Northants County Council and had got permission for a new Vehicle Crossover.

About the project

On our initial site visit we noticed a manhole cover in the middle of where the vehicle crossover was to go, and upon further inspection we found this to be the property of City Fibre. The manhole cover had to be lowered as part of the vehicle crossover works, we also needed to know whether or not the manhole cover was suitable for vehicular traffic, as some of them are not.

We made contact with City Fibre, and unfortunately we were bounced from department to department, and each time we were told that ‘somebody would get back to us’. We had to do a lot of chasing, and the whole process was very frustrating, and it took over 5 weeks to get an agreement from them that they would come and lower the manhole cover.

They agreed to do the work at no extra cost to us or our customer, but it had to be done under our traffic management, and under our Section 184 licence.  

It only took us two weeks to get our Section 184 licence – which we need to ‘dig up the pavement’ and install a vehicle crossover. Our next step was to give notice to Highways and book ‘roadspace’. We have to give three weeks’ notice ordinarily for minor works such as this in Northamptonshire, but we also had to co-ordinate with City Fibre to make sure that they were able to come on the dates that we wanted to book roadspace for. Eventually a date was decided on and we applied to Highways for roadspace and were allocated our preferred dates.

The crossover was on Windmill Avenue in Kettering, a very busy road. We were unable to close the footpath and divert pedestrians onto the other side of the road, and so we had to put up a temporary pedestrian walkway in the road, so pedestrians could safely go around our works.

The excavation of the existing path, putting in new sub-base and new kerbs both at the road and at the boundary with the customer’s private property, took two days. City Fibre came the next day as promised, and the tarmac was laid for the new crossover on day 4.

 

Timeline

Time taken to quote for the works: 1 week

Time taken to obtain Section 184 Licence: 2 weeks

Time take to liaise with City Fibre: 5 weeks

Leadtime to use Licence: 3 weeks

Time taken to do the work: 4 days

Total time: 3 months

Want to know more about the ins and outs of vehicle crossovers? See here and click on the ‘Vehicle Crossovers’ tab for more information. If you want us to quote for a new vehicle crossover, click here, choose ‘Dropped Kerbs/Vehicle Crossovers’ in the drop-down box at the top and upload all the relevant information.

New Vehicle Crossover, Hardwick

Projects

New Vehicle Crossover, Hardwick, Case Study

Location
Hardwick, Cambridgeshire
Client
Private client
Value
Circa £7k
Sewer Connections - Building-Site-Scene - JW Clark

Objective

We were approached our customer in Hardwick, Cambs, for a sewer connection for a new build, which we completed. We were then asked to quote for a vehicle crossover, which the customer had permission to do as part of the planning application. 

About the project

The crossover was a bit involved as it was on a 40mph road, and it was too busy to close the footpath. We had to put up a pedestrian walkway in the road, to safely divert the pedestrians. We excavated the area, which was quite large for a crossover, and was adjacent to a ‘bellmouth’ of a small shopping precinct next door.

We also had a very heavy manhole cover on a surface water catchpit, which had to be lowered. To do this, we had to reduce the ‘corbled masonry’ and fit a modern ‘biscuit’ on top of the catchpit. We re-fitted the original manhole cover as there was nothing wrong with it.

We laid new edging kerbs at the boundary with the new property. At the road we laid new ‘radius’ kerbs to from the entrance onto the crossover. Stone was laid in layers and compacted with a 120mm roller. Tarmac was laid in two stages, with the base course going down in the morning and 6mm tarmac to finish, in the afternoon.

The traffic management was kept up overnight to give the material time to cool down completely. The next day we returned to lay topsoil and grass seed either side of the new crossover, and cleared the site.

Timeline

Timeline

Time taken to quote for the works: 1 week

Time taken to obtain Section 184 Licence: 3 weeks

Leadtime to use Licence: 3 weeks

Time taken to do the work: Less than 1 weeks

Total time: 2 months

 

Testimonial

Our customer was kind enough to leave us a 5-star review on Google:

“Superb company to deal with.
Excellent communication throughout, most helpful in meeting and exceeding time frames all backed up by a great works team who were polite, helpful and supportive whilst on site.
Thank you all 👍👍”

Click here to see more of our Google Reviews

Do you need a crossover doing? Click here and upload your measurements and pictures etc, and we’ll normally get a quote to you within a few days.

Click here to read our FAQs relating to dropped kerbs and vehicle crossovers.

Sewer Connection, Stockport

Projects

Sewer Connection Stockport, Case Study

We were approached by long-time customer of ours Fox Construction of Chapenhall in Scotland. Fox undertake full refurbishments and new construction of Shell Petrol stations throughout the UK. Their job in Turncroft Lane, Stockport required us to make both a surface water and foul connection to the public sewer.

Location
Stockport, Cheshire
Client
Fox Construction Ltd
Value
Circa £39k
Sewer Connections - Building-Site-Scene - JW Clark

Objective

Our objective was to lay surface water pipework from the site boundary of a new Shell Petrol Station in Stockport, and to connect into an existing surface water manhole in the carriageway. And then to do the same for the foul, connection into a manhole again. The surface water was 2m deep, however the foul connection was a bit more challenging, the connection into the existing foul manhole was to be made at 4.3m dig depth. The presence of a Medium Pressure Gas Man within our excavation had to be factored in as to how the works would be carried out. 

About the project

Despite these works being quite challenging in many different ways, traffic management was quite simple on this one. The two connections to the sewer were made at the back of the site, onto a quieter road, and we were therefore able to use ‘give & take’ traffic management.

However, the road was riddled with services including multiple high voltage electric ducts, large water mains, two gas mains (one of them Medium Pressure) and also two very large decommissioned steel mains, likely to have been gas & water. We also had to contend with lower voltage electric cables & BT ducts.

The surface water connection was done first, this required us to excavate in the pavement and a metre into the carriageway, where connection was made into an existing surface water manhole. The depth of this connection was 2 metres. The excavation was sheeted and a third party core-driller was brought in to core-drill the manhole. The pipework was installed, the excavation backfilled, and the manhole was ‘made good’ inside. 

The foul connection required excavation in the footpath also, and then 4 linear metres into the carriageway in the direction of the existing foul manhole. This manhole was 4.3m deep, and United Utilities (owner of the apparatus) required a soffit-to-soffit connection, as is usual for foul connections in particular. The excavation in the carriageway was extensive and required a large pit excavating 4m wide and across half of the carriageway. Within this excavation was an existing Medium Pressure Gas Main, amongst many other services. The presence of the MP Gas Main required us to consult with the owner of the apparatus, Cadent. We put proposals to Cadent which excluded use of the excavator within 1 metre of the Gas Main. Adjacent to the MP main, we had to hand dig, and then the bulk of the excavating was done with a Vacuum Excavator (Vac-Ex), which is basically a big vacuum the size of a very large lorry, see pictures below.

As the MP Gas Main would be passing through our excavation, and the supporting ground dug out from underneath it, the gas main would need to be supported from above. We put proposals to Cadent which included a 5m long steel beam, 150mm x 100mm, placed directly above the gas main. From the steel beam, we strapped the gas main at 500mm centres. Cadent approved all of our proposals and visited site to inspect our method of working, which was all satisfactory to them. 

The excavation at its deepest was 4.3m, which had to be excavated with the Vac-Ex in stages, with us inserting trench sheets, heavy timbers, and acrows as the excavation got deeper. Ordinarily a ‘trench box’ would be lowered into the ground, but with all the services we had to contend with, the excavation had to be sheeted out around and underneath the services. The deepest part of the excavation was directly under the gas main. 

With all of the trench sheeting complete, a third party core-driller was brought in and the manhole core-drilled. The pipework was installed for the foul from the site to the manhole. The manhole was very small inside, for its depth, such as they used to be, this is likely a Victorian-era manhole. As with any manhole entry though, an operative has to be lowered down on a winch, with gas tests done prior and during entry into the manhole. Should anything happen to the operative whilst down the manhole, he would be winched out as opposed to somebody going down there to rescue him. All of our operatives have confined-space training for this reason, which has to be updated and renewed regularly. We cannot undertake new sewer connections without these accreditations, and of course it’s what is needed to keep everybody safe. 

The deep excavation was filled with primary aggregate, with all excavated material having been removed from site. The excavations for both the surface water and foul sewer connection were reinstated at the same time, and the site cleared of all signage and plant & machinery etc.

This was a challenging sewer connection due to the depth of the foul in particular, and also as a result of the Medium Pressure Gas Main, exactly where we didn’t want it. But as always there is a safe method of carrying out these types of works, no matter what the depth and the difficulties involved.

It was a pleasure to have carried out this work for Fox Construction and JW Clark continue to work with Fox Construction on sites across the UK.

Timeline

Time taken to quote for the works: Less than 1 week

Time taken to obtain Section 106 Licence: 4 weeks

Time taken to obtain Section 50 Licence: 10 weeks

Leadtime to use S50 Licence: 3 weeks

Time taken to do the work: 2 weeks

Total time: 20 weeks from enquiry by Fox, to the work being completed

Do you need a sewer connection needs doing? Don’t leave it too late, most people do! Read our article here: How long does it take to do a sewer connection?

 

Stafford Sewer Connections

Projects

Stafford Sewer Connections, Case Study

We were approached by Pritpal of Dulkoo Properties, in Stafford, he had built a new house and needed a connection to the sewer, for both foul and surface water.

Location
Stafford, Staffordshire
Client
Dulkoo Properties
Value
Circa £30k
Sewer Connections - Building-Site-Scene - JW Clark

Objective

Our objective was to make a connection to the surface water connection in the Highway, at 1.5m deep and lay pipework back to the site boundary. The foul connection was a bit trickier at 3.5m deep, and from here we also laid pipework back to the site boundary.

About the project

We met with Stafford Highways to discuss traffic management for the job, and despite the works being on a 3-way junction, we agreed on 2-way traffic lights, but with signage on the side road indicating that traffic on the main road was under signal control. We located the surface water pipe on day 1, on the opposite side of the road to the site. The existing pipe was less than 1.5m deep, and the connection was made using ‘junction insertion’ method. The connection was inspected and passed by Severn Trent Water, and then from the connection point we laid pipework back to the site boundary. The STW Inspector requested that the pipework be concrete-protected, due to how shallow it was in the carriageway. With the surface water pipe laid and the excavation backfilled, we reinstated the Highway to Stafford Highways’ spec. As a Class 1 road, this required in excess of 300mm of tarmac to be laid, in three layers. 

 

The new road surface was allowed to cool overnight, and the traffic lights were switched over in the morning, and excavation was started in preparation for the foul connection. At an invert depth of over 3.5m, we expected to find the top of the 450mm foul sewer at a depth of approx. 3 metres. Due to the depth of the excavation, an extensive amount of trench sheeting and acrow props were required to enable safe entry into the excavation for our operatives. Having excavated down to 2.5m however, and having made the excavation safe, we started to encounter groundwater coming into the sides of the excavation deep down, which were unable to control with pumps. The ground was ‘silty’ and the volume of water made it impossible for us to continue. With the water content we had to deal with and the nature of the ground combined, it is not possible to use pumps to remove the water. We consulted Dewatering Services Ltd whom we have used on a number of occasions, and made plans for them to come to site to ‘dewater’ the ground. Unfortunately they were unable to come there and then, and due to the traffic-sensitive nature of the road, Highways required us to abandon the excavation, reinstate the road and remove the traffic management, which we did. 

 

Just over a week later, we set up the traffic lights all over again….! And Dewatering Services Ltd came to site. In preparation for their arrival, we had re-dug down to a depth of just over two metres, and reinstalled the trench-sheeting system. The Dewatering system included metal rods being pushed 5m into the ground, the whole system was installed in a day. 24 hours later and the excavation had been dried out, we excavated down another metre or so to get to our target depth of 3m, and installed more trench sheets and supports further down. We located the top of the 450mm concrete sewer at 3.15m down from the road level. The concrete sewer was encased in more concrete, which needed to be broken off carefully with a handheld breaker, to gain clear access to the pipe for core-drilling. We instructed a professional core-driller to core-drill into the concrete pipe. With the hole having been cored, we fixed a clay saddle onto the 450mm sewer and secured the saddle and the first clay pipe, with extra-strong and quick-setting mortar. From the connection point we continued to lay 100mm clay pipes towards the boundary. This included excavating under numerous existing services both in the carriageway and in the pavement and cycleway. 

 

The dewatering equipment was removed from site as soon as we came up to 1.5m dig depth, near to the site. The excavation was backfilled and the carriageway, pavement and cycleway all permanently reinstated.  


The project was a reasonably challenging one, due to the dig depth and the water content within the ground. But it is not unusual to encounter groundwater such as this, especially at this depth, and we have plenty of expertise in this area, and often at much deeper depths as well. It was a pleasure to have carried out this work for Pritpal, and we wish him every success with this project and any others we are able to help with going forward. 

Timeline

Time taken to quote for the works: 1 week

Time taken to obtain Section 106 Licence: Our customer already had this

Time taken to obtain Section 50 Licence: The licence only took a few weeks to obtain…. 

Leadtime to use S50 Licence: …….but we had to wait in excess of 3 months before the work could be started, due to other works being undertaken in the area, a road closure around the corner. Highways will not often permit two jobs to run concurrently within a certain radius, and we are never able to carry out works in what is a ‘diversion route’ for another road closure.

Time taken to do the work: 3.5 weeks including us having to go away for a week and then come back with Dewatering Services

Total time: 4.5 months including the delay in being able to use our Section 50 licence, due to other roadworks being carried out in the vicinity. 

Do you need a sewer connection needs doing? Don’t leave it too late, most people do! Read our article here: How long does it take to do a sewer connection?

Stagsden 2 x New Builds

Projects

Stagsden 2 x new builds, Case Study

We were pleased to have been approached by James Taylor from Stagsden, Bedfordshire, and invited to quote for groundwork for 2 x new builds. We had previously worked for James’s father whereby we did the groundwork for another new build, again in Bedfordshire

Location
Stagsden, Bedfordshire
Client
Private customer
Value
Circa £70k
Sewer Connections - Building-Site-Scene - JW Clark

Objective

Our objective was to demolish 3 existing farm buildings, which were to be replaced by 2 new dwellings. We were instructed to carrry out demolition, footings for the new builds, masonry to underside of block and beam, installation of block and beam floor, installation of 2 x treatment plants for the new builds and rainwater drainage including soakaways. 

About the project

Demolition

Our first task on site was to demolish 3 existing farm buildings. Our customer, acting as Principal Contractor, facilitated an asbestos survey, as we suspected at least one of the roofs to be asbestos. The roof was indeed asbestos, and we recommended WJ Redden from Wellingborough, to safely take down the roof and remove the material from site. With the asbestos safely removed, we bought an 8 tonne machine to site, with a grapple bucket attached, and set to demolishing each of the three buildings in turn. The mixed waste was put into skips and removed from site. Any hardcore from the walls and floors was kept on site, to be crushed later on for future use. 

Footings

One of the two barns was to be built with a standard concrete ‘strip’ footing, the drawings detailed 1m dig depth, however we proactively went down to 1.2m due to the top of the dig appearing to be made-up ground. Building Control and the Warranty Provider were happy with the dig, and we continued to pour the concrete footings. On the second barn a piled foundation was required, due to the close proximity of trees on site. The customer had instructed a structural engineer to design the ringbeam, which would sit on the piles. A pile design was put together by the same structural engineer and we instructed a third party piling company. The piles were steel casings driven into the ground, welded together as they were dropped in, and then filled with concrete and reinforcing bars. With the piling complete, we broke off the top of each pile and cut the metal casing on each to the correct height, and then bent the reinforcing bar into where our ringbeam would sit. The ringbeam dig was lined with cellcore to the bottom and then permanent formwork installed all round. The ringbeam was constructed on site and each section lowered in and fixed together. Claymaster was required on the inside of the permanent formwork, all part of the design and as a resut of the trees on site. The concrete ringbeam was poured, completing the foundations for both barns.

Drainage

We installed all foul drainage prior to the masonry being done. This included laying underground drainage pipes to the positions of foul stacks inside each barn for the foul. As there is no public sewer in the village, we installed two treatment plants, one for each barn. These were ‘6-person Marsh Ensign’ treatment plants, a modern-day equivalent of a septic tank. These were installed in full concrete surround as per the manufacturer’s specification. We laid a drainage field for each treatment plant, within the site. Soakaways were installed for rainwater drainage, and pipes laid from the downpipe positions on each house, to the soakaways. 

Masonry

The oversites were reduced to give 200mm clearance under where the block beam would sit, and then we did the masonry to the underside of the block and beam. This consisted of a total of 300mm, so a block and a brick in most places, on both the inner and outer courses. Facework would be done later on by the building contractor doing the superstructure. 

Block and beam

The block and beam was installed, using 150mm beams throughout and 3.5N blocks, and finished with a cement slurry. This concluded this part of the project for us. 

A building contractor was instructed to take over soon after we left, but we expect to return to site at a later date when the new dwellings are built, to install services from the Highway, to each barn. With the services in, we will install a road from the Highway to the new barns, at the moment the road is a hardcore track, suitable for construction traffic throughout the build. 

It was great to have worked with James on this project, especially as we had worked for his Dad on a similar project many years before. And we look forward to returning at a later date to install the services and to put the final road in.

Timeline

Time taken to quote for the works: 2 weeks

Time taken to demolish 3 existing barns and remove waste from site: 1 week

Time taken to install foundations for both barns: Total of 3 weeks including piling contractors coming to site

Time taken to install all drainage: 2.5 weeks including installation of 2 x treatment plants and drainage fields

Time taken to do masonry for both barns: 1 week

Time taken to install block and beam: 1 week

Associated works including site set-up and clearing site at end of project: 1 week

Total time on site: 9.5 weeks